History
ArchitectDan Sima, Mihai Predescu
DesignerNV Construct Cluj-Napoca
Contracted lead designerIntegrated Road Solutions Bucharest
Constructed byStrabag – ARL Cluj
Opened30 May 2025
Location

The Transilvania Bridge in Satu Mare, is a road, pedestrian, and cycling cable-stayed bridge over the Someș River, connecting Independenței Boulevard – Micro 17 neighborhood on the left bank and Henri Coandă Boulevard on the right bank, and overlapping Strandului Street. It is the largest infrastructure project of the city since the 1990s and one of the longest cable stayed bridge in Romania. Inaugurated on 30 May 2025, the bridge is a unique construction in north-western Romania.

History

At the end of 2016 the technical project was tendered, and the contract was awarded to NV Construct Cluj.[1] The cable stayed bridge was designed by subcontractor Integrated Road Solutions and the project was delivered in 2018.

In December 2017 the co-financing contract with the Ministry of Regional Development, Public Administration, and European Funds under PNDL2 was signed.[2]

In 2017 the expropriations were carried out and paid for[3][4]

In 2019 the execution tender was launched, which was awarded to the company Strabag.[5] The construction work for the third bridge over the Someș River in Satu Mare began in 2020.[6]

Characteristics

According to the specialist report, the structure of the third bridge is supported by two pylons, through special steel cables arranged symmetrically in a modified fan design. The cable-stayed assembly, which supports the bridge, has a weight of 216 tons and consists of 56 cables. The cables will support a weight of 12,000 tons. It is a spectacular work that requires a lot of precision and can only be done by a few specialists. The operation will be carried out by the German company DYWIDAG, world leaders in the field.[7][8] Upon completion, the bridge in Satu Mare will be, in terms of span, the third cable-stayed bridge in Romania. It is planned to have four traffic lanes, with two lanes in each direction, two sidewalks with pedestrian barriers, and a bicycle lane. For access from the embankments to the sidewalks of the bridge, four stairs are planned, with two [stairs on each embankment, and for the safety of pedestrian traffic, metal protective barriers will be installed on ramps, viaducts, and the bridge, as well as on the access stairs from the embankments. The bridge over the Someș River – located on Ștrandului Street is a historic investment for Satu Mare, and the Austrian constructor Strabag is mobilizing significant resources to ensure the completion deadline is met.[9]

See also

References

  1. ^ E OFICIAL! Undă VERDE pentru cel de-al treilea pod peste Someș, PresaSM Știri din Satu Mare, 17 November 2016
  2. ^ Satumare (13 December 2017), S-a semnat contractul pentru cel de-al treilea pod peste Someș, Stiri din Satu Mare – Satmareanul
  3. ^ https://old.primariasm.ro/fisiere/pagini_fisiere/Dispozitia_1443_29.11.2017.pdf
  4. ^ Primăria Satu Mare | Hotarari expropriere "POD PESTE RÂUL SOMEȘ", old.primariasm.ro
  5. ^ Pod hobanat peste Someș, la Satu Mare, Economica.net, 21 December 2022
  6. ^ LICITAȚIE FINALIZATĂ PENTRU PODUL PESTE RÂUL SOMEȘ – AMPLASAMENT STR. ȘTRANDULUI, www.primariasm.ro
  7. ^ POD PESTE RÂUL SOMEȘ- AMPLASAMENT STR. ȘTRANDULUI, www.primariasm.ro
  8. ^ VIDEO. Urmează cea mai spectaculoasă și dificilă etapă pentru noul pod peste Someș, PresaSM Știri din Satu Mare, 13 June 2023
  9. ^ POD PESTE RÂUL SOMEȘ- AMPLASAMENT STR. ȘTRANDULUI, www.primariasm.ro